Construction of Isarda Dam Progressing Rapidly to Address Water Supply in Rajasthan
| Aspect | Details |
|---|---|
| Project Name | Isarda Dam Project |
| Location | Banas River near Village Banetha (Tehsil Uniara, District Tonk), downstream of Bisalpur Dam. |
| Districts Benefitted | Dausa (1,079 villages, 5 towns) and Sawai Madhopur (Bundi town, 177 villages, 1 town). |
| Construction Status | 90% completed. Pier and gate works finished; partial work on the earthen dam remains. |
| Phase 1 Completion | Full reservoir level at RL 262 meters (storage capacity 10.77 TMC). Water storage up to RL 256 meters (storage capacity 3.24 TMC) will be utilized initially. |
| Phase 2 Completion | Full storage capacity at RL 262 meters will be achieved. |
| Funding | ₹1038.65 crore approved for Phase 1 under the revised administrative and financial sanctions. |
| Water Sources Managed | Bisalpur Dam's surplus water and Banas River's rainwater. |
| Additional Projects | Ram Jal Setu Link Project (revised PKC-ERCP Link Project) to supply drinking water to Ramgarh Dam, Buchara, Chhitoli dams, and surrounding areas, including Jaipur district. |
| Expected Benefits | Drinking water supply to regions in Dausa and Sawai Madhopur, efficient water management, and water storage during the upcoming monsoon. |